X
GO

Please visit our NEW WEBSITE at www.FSPA.com




Welcome to the Florida Swimming Pool Association – a trade association for companies related to the swimming pool industry.

Current members, login to view additional content.  If you are not yet a member, please take a look at our member advantages and join today!

The Florida Swimming Pool Association was founded in 1959 and has 16 chapters across the state. The 700+ member companies statewide are involved in their local community, sponsoring water safety events and fundraising for local charities, and actively advocate for the swimming pool industry.  Click here to join today.


Mission: Advancing Florida’s swimming pool industry.

To support safety education and swim lessons, visit the Florida Swims Foundation at www.FloridaSwims.org



 
This organization is a silver lever GuideStar participant, demonstrating its committment to transparency.
BELOW THE SURFACE The Industry Blog


Navigating From Contract to Dig
Alyssa / Tuesday, June 15, 2021 / Categories: Blog

Navigating From Contract to Dig

By Ken McKenna, Tampa Bay Pools / ken@tampabaypools.com

What a difference a year makes. Last year, just before COVID, business was good and prices were relatively stable except for your normal increases once a year. Then COVID hits and business blows up. Now as a builder you have to figure out how much business you should take on. How many leads should you take? People say too much business is a good problem, but it is a problem. We spent six or more months navigating through sales and then figuring out the timeline from contract to dig. Then prices start to fluctuate. Now we are seeing pipe triple in cost in just a few months and wood prices souring. The question is how do we sell a pool today that won’t be built for six months and price it accordingly? It is a dilemma I’m sure every builder is wrestling with right now.

I have heard talk of a price escalation clause which, I guess if written properly, works. I worry about the customer’s trust in waiting six months then being told they have to pay more. You could also adjust prices regularly (perhaps monthly) and add a percentage to your typical pricing calculation to cover increases that may arise before construction. You may also want to use a clause in contracts so that if materials aren’t available, substitutes may be used or choices may have to change.

In speaking with many manufacturers, they suggest ordering 12-16 weeks out for anything you need. Now is the time to work closely with all your trade partners to maximize your purchase before the next increase. Also, this may be the time to limit choices on pools to those products that are made domestically and have shorter ordering times. It’s definitely a time for staying on top of costs, saying no to jobs, and trying to maximize your margins instead of increasing volume. Sharing ideas amongst peers is also helpful. There is plenty of work to go around so helping each other may be in all of our best interests. 